From the architects' July 7th Work in Progress report for the
Southside Library: "East Patio bond beam has been poured. Perimeter slab insulation is ongoing. Wall insulation is being attached. Ductwork is ongoing. Steel studs are being finished up. Hydronic systems, water system piping is being installed. The majority of EPDM roof has been done. Metal roof areas have not been done.
"Materials on site: Veneer masonry stone, Rigid insulation under stucco, CMU, Roofing – EPDM / Perlite, Steel framing, Steel fence, Sound attenuators, Ducts, Gypsum sheathing..."