Southside Library. From the architect's Field Report: "Work in progress: a. Masons are finishing the stem wall at the East Patio. Next they will grout all of their CMU. After that is complete, concrete crew will start forming the colored bond beam for the East Patio. Concrete crew is currently forming the steps to Country Club and the monuments signs. b. Sound attenuators are being placed. Two have been secured; six more to go. c. Electrical rough in is ongoing. d. Structural steel at the entrance still needs to be finished as well as the moment connections. e. Exterior walls have been inspected for sheathing."
Construction photos are always available on the Progress Page.