The architect's notes for this week say, "Work in progress: a. Structural concrete at the interior of the building is complete, and the radiant piping is in place at the south side of the building. b. Electricians are installing the conduit for below-slab locations. c. Locations have been laid out for columns outside the heated area of the building."