The architects' notes include: "The steel studs up and going on the north wall of the Café. Structural steel should start getting erected on Tuesday with the arrival of the crane. Forming has begun on the retaining wall on Country Club. The backflow preventer has been installed at the water service. Cistern C and D pads have been poured... The Architect will provide grading drawing for the Children’s Patio so that work may continue."
Other construction photographs are always available on the progress page; and we have pictures from a walkabout on day #160, February 7.